Alaoji Power Plant

Open Cycle was commissioned in March, 2015. The Combined Cycle is at 42% completion and may be completed in 2017.

Operating Company: Alaoji Generation Company Limited
Location: Near Aba, Abia State
EPC Contractor: Rockson Engineering Company Limited
Project Cordinator: Steag West Africa Limited
Configuration: 4 NOs. GE Frame 9E Gas Turbines and 2 NOs. GE Steam Turbines
Capacity: Gas Turbine: 4 x 126MW (ISO) and Steam Turbine: 2 x 286MW

Downloads